How long did the Danone deployment take?

Flowlity recognized as Gartner Cool Vendor 2025 in supply chain planning
Answer:

The Danone project followed Flowlity's standard four-phase implementation. On Day 1, the team held a kick-off and organised workshops to define project scope, use case, and data integration. After two months, continuous data integration from SAP was complete, and the algorithms had been trained using the integrated data sets. After three months, the planning team had access to the application and AI-generated recommendations, and users were sharing their planning and feedback. After six months, the application was implemented and used daily by the procurement team. This phased timeline (data, then test, then production) is what moved the project from kickoff to operational use within six months at the Nutricia plant in Haps.